← Back to Construction Costs

Plastering Costs

Understanding UK plastering labour rates, material costs, and complexity factors.

UK Plastering Labour Rates

Budget: £80-£120/day

Inexperienced plasterers. Basic finishes, visible imperfections acceptable.

Standard: £130-£180/day

Experienced plasterers. Good finish, smooth surfaces, professional standard.

Premium: £190-£250+/day

Specialist plasterers. Perfect finishes, decorative work, superior skill.

Material Costs

Standard plaster (bag): £4-8

Bonding plaster: £5-10

Finishing plaster: £6-12

Plasterboard (per sheet): £6-15

Joint compound/filler: £10-20 per project

Typical project waste: 10-15% material wastage

Types of Plastering Work

Simple Re-plastering (existing walls)

Replastering damaged wall in existing room. Standard rate applies.

Dot & Dab (plasterboard fixing)

Faster than traditional plastering. £100-150/day labour. Simpler, cheaper option.

Skim Finishing

Thin plaster finish on plasterboard. Standard rate, quick work. Usually £25-40/m²

Artex/Textured Finishes

Decorative finishes. Premium rates, requires specialist skill. £40-60/m²

Real Example: Room Replastering (50m²)

Budget Option

Plaster & materials:£60
Labour (3 days):£300
Total:£360

Standard Option

Quality plaster & materials:£80
Labour (3 days):£420
Total:£500

Premium Option (Perfect Finish)

Premium plaster & materials:£120
Labour (4 days, careful work):£800
Total:£920

What Affects Cost?

  • Wall condition: Badly damaged walls need more base coats (higher cost)
  • Substrate type: Brick/block vs old plaster—different techniques cost differently
  • Height/access: High ceilings need scaffolding (adds cost)
  • Straight vs curved: Curved walls need more skill (premium rates)
  • Decorative finishes: Trowel patterns or artex: 50%+ cost increase

Common Misunderstandings

  • "All plaster is the same": Budget vs premium finishes very different
  • "Plaster dries quickly": Actually 2-3 weeks for full cure. Recoating timeline matters
  • "Plasterboard is cheaper than plaster": It is—dot & dab costs £40-60/m² vs plaster £30-40
  • "Imperfections sand out": Major imperfections are hard to fix

Red Flags

  • Quote doesn't specify plaster type (bonding vs finish vs multi-coat)
  • Very fast timescales (plaster needs drying time between coats)
  • No mention of base coat needed for damaged walls
  • Labour rate under £80/day seems suspiciously cheap